A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?
\({ \text{3}}\frac{5}{{12}}\)
\({ \text{3}}\frac{9}{{13}}\)
\({ \text{7}}\frac{5}{{12}}\)
\({ \text{7}}\frac{5}{{13}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A company employed 200 workers to complete a certain work in 150 days. If only \(\frac{1}{4}\) th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were?
Solution |
2
Discuss
|
40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?
Solution |
3
Discuss
|
A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?
Solution |
4
Discuss
|
A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?
Solution |
5
Discuss
|
Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?
Solution |
6
Discuss
|
At a Tech Pvt Ltd. there are some engineering students employed as trainee engineers, belong to two eminent institutions of India. One group belongs to IIT and another to NIT. Each student of IIT works for 10 hours a day till 60 days and each student of NIT works for 8 hours a day till 80 days on the two same project. The ratio of students of IIT and that of NIT is 4:5 respectively. Students of which institution is slower in work and by how much?
Solution |
7
Discuss
|
Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:
Solution |
8
Discuss
|
A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?
Solution |
9
Discuss
|
If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:
Solution |
10
Discuss
|
A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?
Solution |