Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?

Course Name: Quantitative Aptitude

  • 1] 24
  • 2] 20
  • 3] 16
  • 4] 18
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

  • 1]

    8 days

  • 2]

    10 days

  • 3]

    12 days

  • 4]

    15 days

Solution
2
Discuss

A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take ?

  • 1] 15 days
  • 2] 12 days
  • 3] 16 days
  • 4] 14 days
Solution
3
Discuss

The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?

 

  • 1] 4 : 5 : 6
  • 2] 4 : 7 : 5
  • 3] 5 : 7 : 4
  • 4] 5 : 6 : 8
Solution
4
Discuss

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?

  • 1]

    \(\frac{7}{{24}}{ \text{days}}\)

  • 2]

    \({ \text{3}}\frac{3}{7}{ \text{days}}\)

  • 3]

    4 days

  • 4]

    \({ \text{3}}\frac{1}{{13}}{ \text{days}}\)

Solution
5
Discuss

Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?

 

  • 1] 5 hours
  • 2] 8 houras
  • 3] 4 hours
  • 4] 6 hours
Solution
6
Discuss

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

 

  • 1] 2 days
  • 2] 4 days
  • 3] 6 days
  • 4] 8 days
  • 5] 10 days
Solution
7
Discuss

A and B work together to complete the rest of a job in 7 days. However,\(\frac{{37}}{{100}}\) the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

 

  • 1] 20
  • 2] 25
  • 3] 30
  • 4] 10
Solution
8
Discuss

There was a leakage in the container of the refined oil. If 11 kg oil is leaked out per day then it would have lasted for 50 days, if the leakage was 15 kg per day, then it would have lasted for only 45 days. For how many days would the oil have lasted, if there was no leakage ant it was completely used for eating purpose?

  • 1] 80 days
  • 2] 72 days
  • 3] 100 days
  • 4] 120 days
Solution
9
Discuss

A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?

  • 1]

    5

  • 2]

    5 1/2

  • 3]

    6

  • 4]

    8

Solution
10
Discuss

An employee pays Rs. 26 for each day a worker and forfeits Rs. 7 for each day he idle. At the end of 56 days, if the worker got Rs. 829, for how many days did the worker remain idle?

  • 1] 21
  • 2] 15
  • 3] 19
  • 4] 13
  • 5] 17
Solution
# Quiz