A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?

Course Name: Quantitative Aptitude

  • 1]

    \(\frac{{124}}{{13}}\) days

  • 2]

    \(\frac{{113}}{{13}}\) days

  • 3]

    \(\frac{{108}}{{13}}\) days

  • 4]

    \(\frac{{131}}{{13}}\) days

  • 5]

    \(\frac{{120}}{{13}}\) days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?

  • 1] 1 hour
  • 2] 2 hours
  • 3] 3 hours
  • 4] 4 hours
  • 5] 5 hours
Solution
2
Discuss

Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?

  • 1] 3
  • 2] 6
  • 3] 8
  • 4] 12
  • 5] None of these
Solution
3
Discuss

Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?

  • 1] 24
  • 2] 20
  • 3] 16
  • 4] 18
Solution
4
Discuss

A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?

  • 1] 6 days
  • 2] 8 days
  • 3] 15 days
  • 4] 16 days
Solution
5
Discuss

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

  • 1] 30 days
  • 2] 35 days
  • 3] 40 days
  • 4] 45 days
Solution
6
Discuss

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?

  • 1] 20 days
  • 2] 21 days
  • 3] 22 days
  • 4] 24 days
Solution
7
Discuss

Two forest officials in their respective division were involved in the harvesting of tendu leave. One division had an average output of 21 tons from a hectares and other division, which had 12 hectares of land less, dedicated to tendu leaves, got 25 tons of tendu from a hectare. As a result, the second division harvested 300 tons of tendu leaves more than the first. How many tons of tendu leaves did the first division harvest.

  • 1] 3150
  • 2] 3450
  • 3] 3500
  • 4] 3600
  • 5] None of these
Solution
8
Discuss

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

  • 1] 4 days
  • 2] 5 days
  • 3] 6 days
  • 4] 7 days
Solution
9
Discuss

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?

  • 1] 6 hours/day
  • 2] 10 hours/day
  • 3] 12 hours/day
  • 4] 15 hours/day
Solution
10
Discuss

A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?

  • 1]

    \({ \text{14}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    \({ \text{15}}\frac{2}{3}{ \text{ days}}\)

  • 3]

    \({ \text{16}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{18}}\frac{2}{3}{ \text{ days}}\)

Solution
# Quiz