A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?

 

Course Name: Quantitative Aptitude

  • 1] 480
  • 2] 80
  • 3] 200
  • 4] 100
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    12 days

  • 4]

    16 days

Solution
2
Discuss

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

  • 1]

    8 days

  • 2]

    10 days

  • 3]

    12 days

  • 4]

    15 days

Solution
3
Discuss

If 3 men or 9 boys can finish a piece of work in 21 days, in how many days can 5 men and 6 boys together do the same piece of work ?

  • 1] 8 days
  • 2] 12 days
  • 3] 14 days
  • 4] Cannot be determined
  • 5] None of these
Solution
4
Discuss

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?

  • 1] 28 days
  • 2] 36 days
  • 3] 48 days
  • 4] 52 days
Solution
5
Discuss

A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?

  • 1] 4
  • 2] 5
  • 3] 7
  • 4] 8
Solution
6
Discuss

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

  • 1]

    \(9\frac{1}{5}\) days

  • 2]

    \(9\frac{2}{7}\) days

  • 3]

    \(9\frac{3}{5}\) days

  • 4]

    10

Solution
7
Discuss

A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The number of men originally employed were

  • 1]

    12

  • 2]

    15

  • 3]

    18

  • 4]

    24

Solution
8
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
9
Discuss

Amit, Bhawana and Chandan can do a piece of work, working together in one day only. Amit is 5 times efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone ?

  • 1]

    4

  • 2]

    5

  • 3]

    3

  • 4]

    \({ \text{2}}\frac{2}{5}\)

Solution
10
Discuss

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    18 days

Solution