Quiz Discussion

A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?

 

Course Name: Quantitative Aptitude

  • 1] 480
  • 2] 80
  • 3] 200
  • 4] 100
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B together can finish a bit of work in 12 days, B and C can do it in 20 days and C and A do it 15 days. A, B and C together can finish it in

  • 1]

    6 days

  • 2]

    9 days

  • 3]

    10 days

  • 4]

    21/2 days

Solution
2
Discuss

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

  • 1]

    15

  • 2]

    16

  • 3]

    18

  • 4]

    25

Solution
3
Discuss

12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?

  • 1]

    \({ \text{20}}\frac{4}{7}{ \text{ days}}\)

  • 2]

    \({ \text{2}}\frac{4}{7}{ \text{ days}}\)

  • 3]

    \({ \text{20}}\frac{3}{7}{ \text{ days}}\)

  • 4]

    18 days

Solution
4
Discuss

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time in hours that B needs to do the work alone, is ?

  • 1] 18 hours
  • 2] 24 hours
  • 3] 30 hours
  • 4] 12 hours
Solution
5
Discuss

If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?

  • 1] 30
  • 2] 10
  • 3] 18
  • 4] 28
Solution
6
Discuss

A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?

  • 1] 60 days
  • 2] 54 days
  • 3] 48 days
  • 4] 50 days
Solution
7
Discuss

A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?

  • 1]

    \({ \text{3}}\frac{5}{{12}}\)

  • 2]

    \({ \text{3}}\frac{9}{{13}}\)

  • 3]

    \({ \text{7}}\frac{5}{{12}}\)

  • 4]

    \({ \text{7}}\frac{5}{{13}}\)

Solution
8
Discuss

16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?

  • 1] 4 days
  • 2] 6 days
  • 3] 8 days
  • 4] 10 days
Solution
9
Discuss

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

  • 1]

    11 days

  • 2]

    13 days

  • 3]

    20 3/17 days

  • 4]

    None of these

Solution
10
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    \(22\frac{1}{2}\) days

  • 3]

    25 days

  • 4]

    30 days

Solution