A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

Course Name: Quantitative Aptitude

  • 1]

    20 days

  • 2]

    22 1/2 day

  • 3]

    25 days

  • 4]

    30 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
2
Discuss

A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?

  • 1] 2.5 days, 7.5 days
  • 2] 5 days, 8.5 days
  • 3] 5 days, 15 days
  • 4] None of these
Solution
3
Discuss

While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?

  • 1] 3 days
  • 2] 4 days
  • 3] 2.1 days
  • 4] 3.6 days
Solution
4
Discuss

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
5
Discuss

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    12 days

Solution
6
Discuss

A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is = ?

  • 1] 30 days
  • 2] 27 days
  • 3] 20 days
  • 4] 25 days
Solution
7
Discuss

A, B and C completed a work costing Rs. 1800. A worked for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A ?

  • 1] Rs. 600
  • 2] Rs. 750
  • 3] Rs. 800
  • 4] Rs. 900
Solution
8
Discuss

A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take \({ \text{11}}\frac{1}{9}\) days, then the time taken by B alone to do the same work (in days ) is?

 

  • 1] 15 days
  • 2] 20 days
  • 3] 25 days
  • 4] 30 days
Solution
9
Discuss

A man, a woman and a boy can do a piece of work in 6, 9 and 18 days respectively. How many boys must assist one man and one woman to do the work in 1 day ?

  • 1] 5
  • 2] 6
  • 3] 9
  • 4] 13
Solution
10
Discuss

 

A and B together can finish a work in 9 days. A alone can finish the work in 12 days. In how many days will B alone finish the work?

  • 1]

    24

  • 2]

    28

  • 3]

    32

  • 4]

    36

Solution