A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?

Course Name: Quantitative Aptitude

  • 1] 20 days
  • 2] 24 days
  • 3] 36 days
  • 4] 72 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?

  • 1] 60 days
  • 2] 54 days
  • 3] 48 days
  • 4] 50 days
Solution
2
Discuss

Two typists of varying skills can do a job in 6 minutes if they work together. If the first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with \(\frac{1}{5}\) of the whole work. How many minutes would it take the slower typist to complete the typing job working alone?

 

  • 1] 10 minutes
  • 2] 15 minutes
  • 3] 12 minutes
  • 4] 20 minutes
  • 5] 17 minutes
Solution
3
Discuss

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

  • 1]

    \({ \text{6}}\frac{3}{5}\)

  • 2]

    \({ \text{8}}\frac{1}{2}\)

  • 3]

    \({ \text{10}}\frac{1}{5}\)

  • 4]

    \({ \text{13}}\frac{1}{2}\)

Solution
4
Discuss

40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?

  • 1] 6 days
  • 2] 8 days
  • 3] 10 days
  • 4] 12 days
Solution
5
Discuss

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:

  • 1]

    \(9\frac{1}{5}\) days

  • 2]

    \(9\frac{2}{7}\) days

  • 3]

    \(9\frac{3}{5}\) days

  • 4]

    10

Solution
6
Discuss

A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:

  • 1]

    10 hours

  • 2]

    4 hours

  • 3]

    21/4 hours

  • 4]

    24/5 hours

Solution
7
Discuss

A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?

  • 1] 2.5 days, 7.5 days
  • 2] 5 days, 8.5 days
  • 3] 5 days, 15 days
  • 4] None of these
Solution
8
Discuss

A and B together can finish a bit of work in 12 days, B and C can do it in 20 days and C and A do it 15 days. A, B and C together can finish it in

  • 1]

    6 days

  • 2]

    9 days

  • 3]

    10 days

  • 4]

    21/2 days

Solution
9
Discuss

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work ?

  • 1] 10 days
  • 2] 12 days
  • 3] 14 days
  • 4] 16 days
  • 5] None of these
Solution
10
Discuss

A does half as much work as B in one -sixth of the time.If together they take 10 days to complete a work, how much time shall B take to do it alone?