A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?

Course Name: Quantitative Aptitude

  • 1] 20 days
  • 2] 24 days
  • 3] 36 days
  • 4] 72 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A can do a piece of work in 12 days and B in 24 days. If they work together, in how many days will they finish the work ?

  • 1] 20 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
2
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
3
Discuss

A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?

  • 1] Rs. 76
  • 2] Rs. 56
  • 3] Rs. 44
  • 4] Rs. 40
Solution
4
Discuss

Two pipes A and B can fill a cistern in 12 min and 16 min respectively. Both the pipes are opened together for a certain time but due to some obstruction, the flow of water was restricted to \(\frac{7}{8}\) of full flow in pipe A and \(\frac{5}{6}\) of full in pipe B. This obstruction is removed after some time and the tank are now filled in 3 min from that moment. How long was it before the full flow?

 

  • 1] 8 min
  • 2] 3 min
  • 3] 5.6 min
  • 4] 4.5 min
  • 5] None of these
Solution
5
Discuss

If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?

  • 1] 1320
  • 2] 1380
  • 3] 1260
  • 4] 920
Solution
6
Discuss

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?

  • 1] 5 days
  • 2] 6 days
  • 3] 8 days
  • 4] 7 days
Solution
7
Discuss

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

  • 1]

    \({ \text{6}}\frac{3}{5}\)

  • 2]

    \({ \text{8}}\frac{1}{2}\)

  • 3]

    \({ \text{10}}\frac{1}{5}\)

  • 4]

    \({ \text{13}}\frac{1}{2}\)

Solution
8
Discuss

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?

  • 1]

    \(\frac{7}{{24}}{ \text{days}}\)

  • 2]

    \({ \text{3}}\frac{3}{7}{ \text{days}}\)

  • 3]

    4 days

  • 4]

    \({ \text{3}}\frac{1}{{13}}{ \text{days}}\)

Solution
9
Discuss

45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

  • 4]

    \({ \text{7}}\frac{3}{4}{ \text{ days}}\)

Solution
10
Discuss

The daily wages of A and B respectively are Rs. 3.50 and Rs. 2.50. When A finishes a certain work, he gets a total wage of Rs. 63. When B does the same work, he gets a total wage Rs. 75. If both of them do it together what is cost of the work ?

  • 1] Rs. 67.50
  • 2] Rs. 27.50
  • 3] Rs. 60.50
  • 4] Rs. 70.50
Solution
# Quiz