A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?

Course Name: Quantitative Aptitude

  • 1] 16 days
  • 2] 24 days
  • 3] 35 days
  • 4] 28 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution
2
Discuss

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

  • 1]

    15

  • 2]

    16

  • 3]

    18

  • 4]

    25

Solution
3
Discuss

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

  • 1] 30 days
  • 2] 35 days
  • 3] 40 days
  • 4] 45 days
Solution
4
Discuss

A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?

  • 1]

    \({ \text{14}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    \({ \text{15}}\frac{2}{3}{ \text{ days}}\)

  • 3]

    \({ \text{16}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{18}}\frac{2}{3}{ \text{ days}}\)

Solution
5
Discuss

A boy and a girl together fill a cistern with water. The boy pours 4 liters of water every 3 minutes and girl pours 3 litres every 4 minutes. How much time will it take to fill 100 litres of water in the cistern?

  • 1] 36 minute
  • 2] 42 minutes
  • 3] 48 minutes
  • 4] 44 minutes
Solution
6
Discuss

A and B work together to complete the rest of a job in 7 days. However,\(\frac{{37}}{{100}}\) the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

 

  • 1] 20
  • 2] 25
  • 3] 30
  • 4] 10
Solution
7
Discuss

A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?

  • 1]

    \({ \text{6}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    7 days

  • 3]

    \({ \text{7}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{13}}\frac{1}{3}{ \text{ days}}\)

Solution
8
Discuss

A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?

  • 1] 18 days
  • 2] 24 days
  • 3] 9 days
  • 4] 12 days
Solution
9
Discuss

X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.

  • 1] 6 days
  • 2] 8.1 days
  • 3] 5.1 days
  • 4] 7 days
  • 5] None of these
Solution
10
Discuss

Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?

 

  • 1] 5 hours
  • 2] 8 houras
  • 3] 4 hours
  • 4] 6 hours
Solution
# Quiz