A can do a certain job in 12 days and B is 60% more efficient than A. The B can do the same piece of work in ?
\({ \text{8 days}}\)
\({ \text{7}}\frac{1}{2}{ \text{ days}}\)
\({ \text{6}}\frac{1}{4}{ \text{ days}}\)
\({ \text{6 days}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?
Solution |
2
Discuss
|
A is thrice good a workman as B and therefore is able to finish a job in 40 days less than B. Working together they can do it in:
Solution |
3
Discuss
|
A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?
Solution |
4
Discuss
|
If A and B together can complete a work in 18 days, A and C together in 12 days, and B and C together in 9 days, then B alone can do the work in:
Solution |
5
Discuss
|
18 women can complete a work in 12 days and 12 men can complete the same work in 9 days. In how many days will 8 men and 8 women complete that work?
Solution |
6
Discuss
|
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Solution |
7
Discuss
|
Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?
Solution |
8
Discuss
|
A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?
Solution |
9
Discuss
|
The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?
Solution |
10
Discuss
|
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
Solution |