Quiz Discussion

A can complete a piece of work in 36 days, B in 54 days and C in 72 days. All the three began the work the work together but A left 8 days before the completion of the work and B 12 days before the completion of work. Only C worked up to the end. In how many days was the work completed?

Course Name: Quantitative Aptitude

  • 1] 24 days
  • 2] 25 days
  • 3] 27 days
  • 4] 30 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B together can finish a bit of work in 12 days, B and C can do it in 20 days and C and A do it 15 days. A, B and C together can finish it in

  • 1]

    6 days

  • 2]

    9 days

  • 3]

    10 days

  • 4]

    21/2 days

Solution
2
Discuss

Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:

  • 1]

    \(\frac{2}{3}\) hours

  • 2]

    \(\frac{3}{4}\) hours

  • 3]

    \(\frac{3}{2}\) hours

  • 4]

    \(\frac{4}{3}\) hours

Solution
3
Discuss

Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?

  • 1]

    3 : 4

  • 2]

    4 : 3

  • 3]

    5 : 3

  • 4]

    Data Inadequate

Solution
4
Discuss

The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?

 

  • 1] 4 : 5 : 6
  • 2] 4 : 7 : 5
  • 3] 5 : 7 : 4
  • 4] 5 : 6 : 8
Solution
5
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
6
Discuss

A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?

  • 1] 5 days
  • 2] 8 days
  • 3] 3 days
  • 4] 4 days
Solution
7
Discuss

If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it?

  • 1] 10 days
  • 2] 11 days
  • 3] 9 days
  • 4] 12 days
Solution
8
Discuss

If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
9
Discuss

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?

  • 1] 28 days
  • 2] 36 days
  • 3] 48 days
  • 4] 52 days
Solution
10
Discuss

Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?

  • 1] 4 hours
  • 2] 5 hours
  • 3] 6 hours
  • 4] 7 hours
Solution
# Quiz