If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?

Course Name: Quantitative Aptitude

  • 1] 100 days
  • 2] 10 days
  • 3] 5 days
  • 4] 2 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

  • 1] 40 days
  • 2] 50 days
  • 3] 54 days
  • 4] 60 days
Solution
2
Discuss

A is thrice as good a workman as B and so takes 60 days less than B for doing a job. The time in which they can do the job together is = ?

  • 1]

    \(22\frac{1}{2}{ \text{days}}\)

  • 2]

    30 days

  • 3]

    45 days

  • 4]

    60 days

Solution
3
Discuss

P is thrice as good a workman as Q and together they finish a piece of work in 24 days. The number of days taken by P alone to finish the work is:

  • 1]

    25 days

  • 2]

    22 days

  • 3]

    32 days

  • 4]

    34 days

Solution
4
Discuss

A and B working together completed a job in 5 days. If A works twice as efficiently as he actually did and B works \(\frac{1}{3}\) of actual efficiency, the work would have been completed in 3 days. Find the for A to complete the job alone.

 

  • 1]

    \(6\frac{1}{2}\)

  • 2]

    \(6\frac{1}{4}\)

  • 3]

    \(6\frac{3}{4}\)

  • 4]

    \(12\frac{1}{2}\)

  • 5]

    None of these

Solution
5
Discuss

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?

  • 1] 100
  • 2] 110
  • 3] 55
  • 4] 50
Solution
6
Discuss

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

  • 1] 4 days
  • 2] 2 days
  • 3] 1 day
  • 4] 10 days
Solution
7
Discuss

A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?

  • 1]

    \({ \text{3}}\frac{5}{{12}}\)

  • 2]

    \({ \text{3}}\frac{9}{{13}}\)

  • 3]

    \({ \text{7}}\frac{5}{{12}}\)

  • 4]

    \({ \text{7}}\frac{5}{{13}}\)

Solution
8
Discuss

A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
9
Discuss

Two pipes can fill an empty tank separately in 24 minutes and 40 minutes respectively and a third pipe can empty 30 gallons of water per minute. If all three pipes are open, empty tanks become full in one hour. The capacity of the tank (in gallons) is:

  • 1] 800 gallons
  • 2] 600 gallons
  • 3] 500 gallons
  • 4] 400 gallons
Solution
10
Discuss

A completes \(\frac{7}{{10}}\) of the work 15 days. Then he completes the remaining work the help of B in 4 days. The time required for A and B together to complete the entire work is = ?

 

  • 1]

    \({ \text{8}}\frac{1}{4}{ \text{days}}\)

  • 2]

    \(10\frac{1}{2}{ \text{days}}\)

  • 3]

    \(12\frac{2}{3}{ \text{days}}\)

  • 4]

    \(13\frac{1}{3}{ \text{days}}\)

Solution