If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?

Course Name: Quantitative Aptitude

  • 1] 100 days
  • 2] 10 days
  • 3] 5 days
  • 4] 2 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

  • 1] 5 days
  • 2] 6 days
  • 3] 9 days
  • 4] 10 days
Solution
2
Discuss

If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?

  • 1] 260
  • 2] 240
  • 3] 280
  • 4] 520
Solution
3
Discuss

While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?

  • 1] 3 days
  • 2] 4 days
  • 3] 2.1 days
  • 4] 3.6 days
Solution
4
Discuss

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

  • 1]

    15

  • 2]

    16

  • 3]

    18

  • 4]

    25

Solution
5
Discuss

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  • 1]

    30 days

  • 2]

    40 days

  • 3]

    60 days

  • 4]

    70 days

Solution
6
Discuss

If 3 men or 9 boys can finish a piece of work in 21 days, in how many days can 5 men and 6 boys together do the same piece of work ?

  • 1] 8 days
  • 2] 12 days
  • 3] 14 days
  • 4] Cannot be determined
  • 5] None of these
Solution
7
Discuss

60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?

  • 1] 10
  • 2] 15
  • 3] 18
  • 4] 20
Solution
8
Discuss

 

A and B together can finish a work in 9 days. A alone can finish the work in 12 days. In how many days will B alone finish the work?

  • 1]

    24

  • 2]

    28

  • 3]

    32

  • 4]

    36

Solution
9
Discuss

X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.

  • 1] 6 days
  • 2] 8.1 days
  • 3] 5.1 days
  • 4] 7 days
  • 5] None of these
Solution
10
Discuss

A and B working together completed a job in 5 days. If A works twice as efficiently as he actually did and B works \(\frac{1}{3}\) of actual efficiency, the work would have been completed in 3 days. Find the for A to complete the job alone.

 

  • 1]

    \(6\frac{1}{2}\)

  • 2]

    \(6\frac{1}{4}\)

  • 3]

    \(6\frac{3}{4}\)

  • 4]

    \(12\frac{1}{2}\)

  • 5]

    None of these

Solution