18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?
Solution |
2
Discuss
|
40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?
Solution |
3
Discuss
|
A is thrice good a workman as B and therefore is able to finish a job in 40 days less than B. Working together they can do it in:
Solution |
4
Discuss
|
A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?
Solution |
5
Discuss
|
Two typists of varying skills can do a job in 6 minutes if they work together. If the first typist typed alone for 4 minutes and then the second typist typed alone for 6 minutes, they would be left with \(\frac{1}{5}\) of the whole work. How many minutes would it take the slower typist to complete the typing job working alone?
Solution |
6
Discuss
|
If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?
Solution |
7
Discuss
|
Two pipes, P and Q can fill a cistern in 12 and 15 minutes respectively. Both are opened together, but at the end of 3 minutes, P is turned off. In how many more minutes will Q fill the cistern?
Solution |
8
Discuss
|
A and B together can finish a work in 9 days. A alone can finish the work in 12 days. In how many days will B alone finish the work?
Solution |
9
Discuss
|
A pipe can fill a tank in 0.9 hours and another pipe can empty in 0.7 hours. If tank is completely filled and both pipes are opened simultaneously then 450 liters of water is removed from the tank is 2.5 hours. What is the capacity of the tank?
Solution |
10
Discuss
|
A does half as much work as B in one -sixth of the time.If together they take 10 days to complete a work, how much time shall B take to do it alone?
Solution |