A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?
\({ \text{6}}\frac{1}{3}{ \text{ days}}\)
7 days
\({ \text{7}}\frac{1}{3}{ \text{ days}}\)
\({ \text{13}}\frac{1}{3}{ \text{ days}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?
Solution |
2
Discuss
|
Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?
Solution |
3
Discuss
|
Working efficiencies of P and Q for completing a piece of working are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?
Solution |
4
Discuss
|
A cistern can be filled by two pipes in 20 and 30 minutes respectively. Both pipes being opened, when the first pipe must be turned off so that the cistern may be filled in 10 minutes more.
Solution |
5
Discuss
|
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Solution |
6
Discuss
|
A completed \(\frac{7}{{10}} \)of work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many days A and B can complete the entire work together?
Solution |
7
Discuss
|
A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?
Solution |
8
Discuss
|
3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?
Solution |
9
Discuss
|
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Solution |
10
Discuss
|
A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone ?
Solution |