Quiz Discussion

A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?

Course Name: Python

  • 1] 18 days
  • 2] 24 days
  • 3] 9 days
  • 4] 12 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

  • 1] 20 days
  • 2] 10 days
  • 3] 4 days
  • 4] 15 days
Solution
2
Discuss

A can do as much work as B and C together can do. A and B can together do a piece of work in 9 hours 36 minutes and C can do it in 48 hours. The time in hours that B needs to do the work alone, is ?

  • 1] 18 hours
  • 2] 24 hours
  • 3] 30 hours
  • 4] 12 hours
Solution
3
Discuss

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?

  • 1] 8 days
  • 2] 6 days
  • 3] 8 days
  • 4] 12 days
Solution
4
Discuss

X can copy 80 pages in 20 hours, x and y together can copy 135 pages in 27 hours. Then y can copy 20 pages in ?

  • 1] 20 hours
  • 2] 24 hours
  • 3] 3 hours
  • 4] 12 hours
Solution
5
Discuss

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?

  • 1] 20 days
  • 2] 21 days
  • 3] 22 days
  • 4] 24 days
Solution
6
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
7
Discuss

P and Q together can do a job in 6 days. Q and R can finish the same job in \(\frac{{60}}{7}\) days. P started the work and worked for 3 days. Q and R continued for 6 days to finish the work. Then the difference of days in which R and P can complete the alone is P can complete the job alone is ?

 

  • 1] 10 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
8
Discuss

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone ?

  • 1] 10 days
  • 2] 9 days
  • 3] 12 days
  • 4] 15 days
Solution
9
Discuss

A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?

  • 1] 60 days
  • 2] 54 days
  • 3] 48 days
  • 4] 50 days
Solution
10
Discuss

A can do a work in 10 days. The efficiency of A is 20% less than B. How many days B need to finish the same work?

  • 1] 8.5 days
  • 2] 12.3 days
  • 3] 8 days
  • 4] 7.5 days
Solution
# Quiz