Working efficiencies of P and Q for completing a piece of working are in the ratio 3 : 4. The number of days to be taken by them to complete the work will be in the ratio ?

Course Name: Python

  • 1] 3 : 2
  • 2] 2 : 3
  • 3] 3 : 4
  • 4] 4 : 3
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?

 

  • 1] 2 days
  • 2] 4 days
  • 3] 6 days
  • 4] 8 days
  • 5] 10 days
Solution
2
Discuss

The daily wages of A and B respectively are Rs. 3.50 and Rs. 2.50. When A finishes a certain work, he gets a total wage of Rs. 63. When B does the same work, he gets a total wage Rs. 75. If both of them do it together what is cost of the work ?

  • 1] Rs. 67.50
  • 2] Rs. 27.50
  • 3] Rs. 60.50
  • 4] Rs. 70.50
Solution
3
Discuss

A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?

 

  • 1]

    \({ \text{ 7}}\frac{3}{8}{ \text{ days}}\)

  • 2]

    \({ \text{8}}\frac{4}{5}{ \text{ days}}\)

  • 3]

    \({ \text{9}}\frac{3}{8}{ \text{ days}}\)

  • 4]

    10 days

Solution
4
Discuss

Raj can do a piece of work in 20 days. He started the work and left after some days, when 25% work was done. After it Abhijit joined and completed it working for 10 days. In how many days Raj and Abhijit can do the complete work, working together?

  • 1] 6
  • 2] 8
  • 3] 10
  • 4] 12
Solution
5
Discuss

A's 2 days work is equal to B's 3 days work. If A can complete the work in 8 days, then to complete the work B will take ?

  • 1] 15 days
  • 2] 12 days
  • 3] 16 days
  • 4] 14 days
Solution
6
Discuss

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?

  • 1] 75
  • 2] 100
  • 3] 125
  • 4] 50
Solution
7
Discuss

A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?

  • 1] 16 days
  • 2] 24 days
  • 3] 35 days
  • 4] 28 days
Solution
8
Discuss

If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?

  • 1] 100 days
  • 2] 10 days
  • 3] 5 days
  • 4] 2 days
Solution
9
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
10
Discuss

If m men can do a work in r days, then the number of days taken by (m + n) men to do it is :

  • 1]

    \(\frac{{{ \text{m}} + { \text{n}}}}{{{ \text{mn}}}}\)

  • 2]

    \(\frac{{{ \text{m}} + { \text{n}}}}{{{ \text{mr}}}}\)

  • 3]

    \(\frac{{{ \text{mr}}}}{{{ \text{m}} + { \text{n}}}}\)

  • 4]

    \(\frac{{{ \text{r}}\left( {{ \text{m}} + { \text{n}}} \right)}}{{{ \text{mn}}}}\)