A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?
Solution |
2
Discuss
|
A single reservoir supplies the petrol to the whole city, while the reservoir is fed by a single pipeline filling the reservoir with the stream of uniform volume. When the reservoir is full and if 40, 000 litres of petrol is used daily, the supply fails in 90 days. If 32, 000 litres of petrol used daily, it fails in 60 days. How much petrol can be used daily without the supply ever failing?
Solution |
3
Discuss
|
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?
Solution |
4
Discuss
|
Working together, Asha and Sudha can complete an assigned task in 20 days. However, if Asha worked alone and completed half the work and then Sudha takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Asha take to complete the if she worked alone ? Assume that Sudha is more efficient than Asha.
Solution |
5
Discuss
|
Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take \({ \text{4}}\frac{1}{2}\) hours more than when working together. The time required to finish the work together is =?
Solution |
6
Discuss
|
16 men can finish a piece of work in 49 days. 14 men started working and 8 days they could finish certain amount of work. If it is required to finish the remaining work in 24 days. How many more men should be added to the existing workforce ?
Solution |
7
Discuss
|
A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?
Solution |
8
Discuss
|
If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:
Solution |
9
Discuss
|
Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?
Solution |
10
Discuss
|
Two pipes, P and Q can fill a cistern in 12 and 15 minutes respectively. Both are opened together, but at the end of 3 minutes, P is turned off. In how many more minutes will Q fill the cistern?
Solution |