Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can do a piece of work in 5 days less than the time taken by B to do it. If both of them together take \({ \text{11}}\frac{1}{9}\) days, then the time taken by B alone to do the same work (in days ) is?
Solution |
2
Discuss
|
A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?
Solution |
3
Discuss
|
A job can be done by 3 skilled workmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together ?
Solution |
4
Discuss
|
A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
Solution |
5
Discuss
|
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?
Solution |
6
Discuss
|
If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?
Solution |
7
Discuss
|
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is = ?
Solution |
8
Discuss
|
Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:
Solution |
9
Discuss
|
Five men are working to complete a work in 15 days. After five days 10 women are accompanied by them to complete the work in next 5 days. If the work is to be done by women only, then in how many days could the work be over if 10 women have started it ?
Solution |
10
Discuss
|
A tank can be filled with water by two pipes A and B together in 36 minutes. If the pipe B was stopped after 30 minutes, the tank is filled in 40 minutes. The pipe B can alone fill the tank in:
Solution |