A man and a boy received Rs. 800 as wages for 5 days for the work they did together. The man's efficiency in the work was thrice times that of the boy. What are the daily wages of the boy?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for ?
Solution |
2
Discuss
|
X takes 4 days to complete one-third of a job. Y takes 3 days to complete one-sixth of the job and Z takes 5 days to complete half the job. If all of them work together for 3 days and X and Z quit, how long will it take for Y to complete the remaining work done.
Solution |
3
Discuss
|
A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?
Solution |
4
Discuss
|
4 mat-weavers can weave 4 mats in 4 days. At the same rate how many mats would be woven by 8 mat-weavers in 8 days ?
Solution |
5
Discuss
|
A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C together for 2 days and A was replaced by B. In how many days, altogether, was the work complete ?
Solution |
6
Discuss
|
A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?
Solution |
7
Discuss
|
Amit, Bhawana and Chandan can do a piece of work, working together in one day only. Amit is 5 times efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone ?
Solution |
8
Discuss
|
3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?
Solution |
9
Discuss
|
A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?
Solution |
10
Discuss
|
If 4 men or 6 women can do a piece of work in 12 days working 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day ?
Solution |