A and B together can complete a work in 12 days. B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work ?
\({ \text{3}}\frac{5}{{12}}\)
\({ \text{3}}\frac{9}{{13}}\)
\({ \text{7}}\frac{5}{{12}}\)
\({ \text{7}}\frac{5}{{13}}\)
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
42 women can do a piece of work in 18 days, How many women would be required do the same work in 21 days.
Solution |
2
Discuss
|
A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?
Solution |
3
Discuss
|
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Solution |
4
Discuss
|
Three men A, B, C working together can do a job in 6 hours less time than A alone, in one hour less time than B alone and in one half the time needed by C when working alone. Then A and B together can do the job in:
Solution |
5
Discuss
|
12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?
Solution |
6
Discuss
|
A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?
Solution |
7
Discuss
|
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Solution |
8
Discuss
|
A and B undertake a piece of work for Rs. 250. A alone can do that work in 5 days and B alone can do that work in 15 days. With the help of C, they finish the work in 3 days. If every one gets paid in proportion to work done by them, the amount C will get is ?
Solution |
9
Discuss
|
X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?
Solution |
10
Discuss
|
A does 20% less work than B. If A can complete a piece of work in \({ \text{7}}\frac{1}{2}\) hours, then B can do it in?
Solution |