Quiz Discussion

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :

Course Name: Quantitative Aptitude

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    18 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • 1]

    \(7\frac{1}{2}\)

  • 2]

    10

  • 3]

    12

  • 4]

    14

Solution
2
Discuss

A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?

  • 1] 1 : 2 : 4
  • 2] 2 : 1 : 4
  • 3] 4 : 2 : 1
  • 4] 2 : 4 : 1
Solution
3
Discuss

A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for ?

  • 1] 12 days
  • 2] 13 days
  • 3] 14 days
  • 4] 15 days
Solution
4
Discuss

If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?

  • 1] 1320
  • 2] 1380
  • 3] 1260
  • 4] 920
Solution
5
Discuss

If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?

  • 1] 35 days
  • 2] 50 days
  • 3] 45 days
  • 4] 40 days
Solution
6
Discuss

Ram Lal is a renowned packager of fruits in Varanasi. He packs 70 mangoes or 56 guavas every day working 7 hours a day. His wife also helps him. She packs 30 mangoes or 24 guavas working 6 hours per day. Ram Lal has to pack 3300 mangoes and 2400 guavas with help of his wife. They works alternately, each day 10 hours. His wife started packaging firs day and works every alternate days. Similarly, Ram Lal started his work second day and and worked alternatively till the completion of the work. In how many days the work will finished?

  • 1]

    \(85\frac{3}{2}\)

  • 2]

    85

  • 3]

    84

  • 4]

    80

  • 5]

    None of these

Solution
7
Discuss

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ?

  • 1] 100
  • 2] 60
  • 3] 75
  • 4] None of these
Solution
8
Discuss

To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

  • 1] 30 days
  • 2] 35 days
  • 3] 40 days
  • 4] 45 days
Solution
9
Discuss

A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
10
Discuss

A can do \(\frac{1}{3}\) rd of work in 5 days and B can do the do \(\frac{2}{5}\)th of this work in 10 days. Both A and B, together can do the work in?

 

  • 1]

    \({ \text{ 7}}\frac{3}{8}{ \text{ days}}\)

  • 2]

    \({ \text{8}}\frac{4}{5}{ \text{ days}}\)

  • 3]

    \({ \text{9}}\frac{3}{8}{ \text{ days}}\)

  • 4]

    10 days

Solution
# Quiz