To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?
Solution |
2
Discuss
|
A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
Solution |
3
Discuss
|
60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?
Solution |
4
Discuss
|
20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed ?
Solution |
5
Discuss
|
Two pipes A and B can fill a tank in 36 min. and 45 min. respectively. Another pipe C can empty the tank in 30 min. First A and B are opened. After 7 minutes, C is also opened. The tank filled up in:
Solution |
6
Discuss
|
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
Solution |
7
Discuss
|
A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?
Solution |
8
Discuss
|
A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?
Solution |
9
Discuss
|
A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for
Solution |
10
Discuss
|
A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?
Solution |