A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

Course Name: Quantitative Aptitude

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
2
Discuss

If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:

  • 1] 12 days
  • 2] 10 days
  • 3] 9 days
  • 4] 8 days
Solution
3
Discuss

A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is = ?

  • 1] 100 days
  • 2] 96 days
  • 3] 95 days
  • 4] 90 days
Solution
4
Discuss

12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?

  • 1] 4 minutes
  • 2] 10 minutes
  • 3] 12 minutes
  • 4] 8 minutes
Solution
5
Discuss

X alone can complete a piece of work in 40 days. He worked for 8 days and left. Y alone completed the remaining work in 16 days. How long would X and Y together take to complete the work ?

  • 1]

    \(13\frac{1}{3}{ \text{days}}\)

  • 2]

    14 days

  • 3]

    15 days

  • 4]

    \(16\frac{2}{3}{ \text{days}}\)

Solution
6
Discuss

A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
7
Discuss

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  • 1]

    30 days

  • 2]

    40 days

  • 3]

    60 days

  • 4]

    70 days

Solution
8
Discuss

A can do a piece of work in 4 hours, B and C together in 3 hours, and A and C together in 2 hours. How long will B alone take to do it ?

  • 1] 8 hours
  • 2] 10 hours
  • 3] 12 hours
  • 4] 24 hours
Solution
9
Discuss

Three friends Anne, Bob and Chris work together to do a certain job. Time it takes them to do the work together to do a certain job. The it takes them to do the work together is 6 hours less than Anne would have take alone, 1 hour less than Bob would have taken alone and half the time Chris would have taken working alone text. How long did it take them to complete the job, working together ?

  • 1] 20 minutes
  • 2] 30 minutes
  • 3] 40 minutes
  • 4] 50 minutes
Solution
10
Discuss

If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?

  • 1] 35 days
  • 2] 50 days
  • 3] 45 days
  • 4] 40 days
Solution