Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

Course Name: Quantitative Aptitude

  • 1]

    \(7\frac{1}{2}\)

  • 2]

    10

  • 3]

    12

  • 4]

    14

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?

  • 1] 5 days
  • 2] 6 days
  • 3] 8 days
  • 4] 7 days
Solution
2
Discuss

A group of men decided to do a job in 4 days. But since 20 men dropped out every day, the job completed at the end of the 7th day. How many men were there at the beginning?

  • 1] 240
  • 2] 140
  • 3] 280
  • 4] 150
  • 5] None of these
Solution
3
Discuss

A and B together can do a piece of work in 30 days, B and C together can do it in 20 days, A starts the work and works on it for 5 days, B takes up and work for 15 days. Finally C finishes the work in 18 days. The number of days in which C alone can do the work where doing it separately is = ?

  • 1] 120 days
  • 2] 40 days
  • 3] 60 days
  • 4] 24 days
Solution
4
Discuss

If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
5
Discuss

Two persons having different productivity of labour, working together can reap a field in 2 days. If one-third of the field was reaped by the first man and rest by the other one working alternatively took 4 days. How long did it take for the faster person to reap the whole field working alone?

  • 1] 3
  • 2] 6
  • 3] 8
  • 4] 12
  • 5] None of these
Solution
6
Discuss

If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?

  • 1] 100 days
  • 2] 10 days
  • 3] 5 days
  • 4] 2 days
Solution
7
Discuss

A, B and C completed a work costing Rs. 1800. A work for 6 days, B for 4 days and C for 9 days. If their daily wages are in the ratio of 5 : 6 : 4, how much amount will be received by A?

  • 1] Rs. 800
  • 2] Rs. 600
  • 3] Rs. 900
  • 4] Rs. 750
Solution
8
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    \(22\frac{1}{2}\) days

  • 3]

    25 days

  • 4]

    30 days

Solution
9
Discuss

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

  • 1] Rs. 375
  • 2] Rs. 400
  • 3] Rs. 600
  • 4] Rs. 800
Solution
10
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution