A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The number of men originally employed were
12
15
18
24
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?
Solution |
10
Discuss
|
Two workers A and B are engaged to do a work. A working alone takes 8 hours more to complete the job than if both worked together. If B worked alone, he would need 41/2 hours more to complete the job than they both working together. What time would they take to do the work together ?
Solution |
2
Discuss
|
A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?
Solution |
3
Discuss
|
Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?
Solution |
4
Discuss
|
If one pipe A can fill a tank in 20 minutes, then 5 pipes, each of 20% efficiency of A, can fill the tank in:
Solution |
5
Discuss
|
A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?
Solution |
6
Discuss
|
If 28 men complete 78 of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?
Solution |
7
Discuss
|
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
Solution |
8
Discuss
|
Two pipes can fill the cistern in 10hr and 12 hr respectively, while the third empty it in 20hr. If all pipes are opened simultaneously, then the cistern will be filled in:
Solution |
9
Discuss
|
A and B together can finish a work in 9 days. A alone can finish the work in 12 days. In how many days will B alone finish the work?
Solution |
# | Quiz |
Copyright © 2020 Inovatik - All rights reserved