A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in ?

Course Name: Quantitative Aptitude

  • 1]

    \({ \text{14}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    \({ \text{15}}\frac{2}{3}{ \text{ days}}\)

  • 3]

    \({ \text{16}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{18}}\frac{2}{3}{ \text{ days}}\)

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:

  • 1] 4 days
  • 2] 5 days
  • 3] 6 days
  • 4] 7 days
Solution
2
Discuss

A can do a piece of work in 70 days and B is 40% more efficient then A. Then the number of days taken by B to do the same work is = ?

  • 1] 40 dayd
  • 2] 60 days
  • 3] 50 days
  • 4] 45 days
Solution
3
Discuss

If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:

  • 1] 12 days
  • 2] 10 days
  • 3] 9 days
  • 4] 8 days
Solution
4
Discuss

16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?

  • 1] 4 days
  • 2] 6 days
  • 3] 8 days
  • 4] 10 days
Solution
5
Discuss

The charges per hour of internet surfing is increased by 25% then find the percentage decrease in the time period of surfing user (a net savy) who can afford only 10% increase in expenditure:

  • 1] 22%
  • 2] 12%
  • 3] 15%
  • 4] 9.09%
Solution
6
Discuss

If the work done by (x - 1) men in (x + 1) days and the work done by (x + 2) men in (x - 1) days are in the ratio 9 : 10, then the value of x is equal to ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
7
Discuss

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. In how many days C alone can do the same work ?

  • 1] 5 days
  • 2] 6 days
  • 3] 10 days
  • 4] 12 days
Solution
8
Discuss

A, B and C can separately do a work in 12, 15 and 20 days respectively. They started to work together but C left after 2 days. The remaining work will be finished in = ?

  • 1] 4 days
  • 2] 5 days
  • 3] 6 days
  • 4] 15 days
Solution
9
Discuss

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

  • 1]

    \(\frac{1}{4}\)

  • 2]

    \(\frac{1}{{10}}\)

  • 3]

    \(\frac{7}{{15}}\)

  • 4]

    \(\frac{8}{{15}}\)

Solution
10
Discuss

A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are ?

  • 1] Rs. 150
  • 2] Rs. 225
  • 3] Rs. 250
  • 4] Rs. 300
Solution