45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?

Course Name: Quantitative Aptitude

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    623 days

  • 4]

    734 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

#Quiz
1
Discuss

Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?

  • 1] Rs. 600, Rs. 550, Rs. 250
  • 2] Rs. 600, Rs. 525, Rs. 275
  • 3] Rs. 600, Rs. 500, Rs. 300
  • 4] Rs. 500, Rs. 525, Rs. 375
Solution
10
Discuss

If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?

  • 1] 260
  • 2] 240
  • 3] 280
  • 4] 520
Solution
2
Discuss

If 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days, then 10 women complete it in ?

  • 1] 35 days
  • 2] 50 days
  • 3] 45 days
  • 4] 40 days
Solution
3
Discuss

There is provision of food in fort for 1200 soldiers for 60 days. After 15 days, 200 soldiers leave the fort. Remaining food will last for how many days?

  • 1] 56 days
  • 2] 50 days
  • 3] 54 days
  • 4] 48 days
Solution
4
Discuss

A can do a piece of work in 15 days, which B can do it in 10 days. B worked at it for 8 days. A can finish the remaining work in?

  • 1] 2 days
  • 2] 3 days
  • 3] 5 days
  • 4] 10 days
Solution
5
Discuss

8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work ?

  • 1] 10 days
  • 2] 12 days
  • 3] 14 days
  • 4] 16 days
  • 5] None of these
Solution
6
Discuss

Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?

  • 1] 14
  • 2] 17
  • 3] 12
  • 4] 15
Solution
7
Discuss

A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was ?

  • 1] 100
  • 2] 110
  • 3] 55
  • 4] 50
Solution
8
Discuss

To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

  • 1] 7 Days
  • 2] 7.5 Days
  • 3] 8 Days
  • 4] 8.5 Days
Solution
9
Discuss

If one pipe A can fill a tank in 20 minutes, then 5 pipes, each of 20% efficiency of A, can fill the tank in:

  • 1] 80 min
  • 2] 100 min
  • 3] 20 min
  • 4] 25 min
Solution
#Quiz
Showing 1 to 10 of 10 entries