60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?
Solution |
2
Discuss
|
A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:
Solution |
3
Discuss
|
Working together B and C take 50% more number of days than A, B and C together take and A and B working together, take \(\frac{8}{3} \)more number of days than A, B and C take together. If A, B, and C all have worked together till the completion of the work and B has received Rs. 120 out of total earnings of Rs. 450, then in how many days did A, B and C together complete the whole work?
Solution |
4
Discuss
|
A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?
Solution |
5
Discuss
|
A can write 75 pages in 25 hours. A and B together can write 135 pages in 27 hours. In what time can B write 42 pages ?
Solution |
6
Discuss
|
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in :
Solution |
7
Discuss
|
A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?
Solution |
8
Discuss
|
A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?
Solution |
9
Discuss
|
A labourer was appointed by a contractor on the condition he would be paid Rs. 75 for each day of his work but would be, fined at the rate of Rs. 15 per day for his absent. After 20 days, the contractor paid the labourer Rs. 1140. The number of days the labourer absented from work was ?
Solution |
10
Discuss
|
A company employed 200 workers to complete a certain work in 150 days. If only \(\frac{1}{4}\) th of the work had been done in 50 days, then in order to complete the whole work in time, the number of additional workers to be employed were?
Solution |