Quiz Discussion

A can do a piece of work in 12 days and B in 24 days. If they work together, in how many days will they finish the work ?

Course Name: Quantitative Aptitude

  • 1] 20 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

Two pipes A and B can fill a cistern in 12 min and 16 min respectively. Both the pipes are opened together for a certain time but due to some obstruction, the flow of water was restricted to \(\frac{7}{8}\) of full flow in pipe A and \(\frac{5}{6}\) of full in pipe B. This obstruction is removed after some time and the tank are now filled in 3 min from that moment. How long was it before the full flow?

 

  • 1] 8 min
  • 2] 3 min
  • 3] 5.6 min
  • 4] 4.5 min
  • 5] None of these
Solution
2
Discuss

Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?

  • 1] Rs. 600, Rs. 550, Rs. 250
  • 2] Rs. 600, Rs. 525, Rs. 275
  • 3] Rs. 600, Rs. 500, Rs. 300
  • 4] Rs. 500, Rs. 525, Rs. 375
Solution
3
Discuss

60 men could complete a piece of work in 250 days. They worked together for 200 days. After that work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time ?

  • 1] 10
  • 2] 15
  • 3] 18
  • 4] 20
Solution
4
Discuss

A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?

  • 1] 30 days
  • 2] 40 days
  • 3] 50 days
  • 4] 70 days
Solution
5
Discuss

A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?

 

  • 1] 120 days
  • 2] 100 days
  • 3] 30 days
  • 4] 90 days
Solution
6
Discuss

A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?

  • 1] 4 days
  • 2] 6 days
  • 3] 9 days
  • 4] 18 days
Solution
7
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
8
Discuss

A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?

  • 1]

    \({ \text{6}}\frac{1}{3}{ \text{ days}}\)

  • 2]

    7 days

  • 3]

    \({ \text{7}}\frac{1}{3}{ \text{ days}}\)

  • 4]

    \({ \text{13}}\frac{1}{3}{ \text{ days}}\)

Solution
9
Discuss

18 men can complete a piece of work in 63 days. 9 women take 189 days to complete the same piece of work. How many days will 4 men, 9 women and 12 children together take to complete the piece of work if 7 children alone can complete the piece of work in 486 days ?

  • 1] 54 days
  • 2] 63 days
  • 3] 76 days
  • 4] 81 days
  • 5] None of these
Solution
10
Discuss

If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?

  • 1] 30
  • 2] 10
  • 3] 18
  • 4] 28
Solution
# Quiz