A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

Course Name: Quantitative Aptitude

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If 2 men or 6 women or 4 boys can finish a work in 99 days, how many days will one man, one woman and one boy together take to finish the same work ?

  • 1] 44 days
  • 2] 54 days
  • 3] 64 days
  • 4] 104 days
  • 5] None of these
Solution
2
Discuss

Shashi can do piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is = ?

  • 1] 15
  • 2] 25
  • 3] 18
  • 4] 16
Solution
3
Discuss

A can build a wall in the same time in which B and C together can do it. If A and B together can do it. If A and B together could do it in 25 days and C alone in 35 days, in what time could B alone do it ?

  • 1] 91 days
  • 2] 100 days
  • 3] 175 days
  • 4] None of these
Solution
4
Discuss

A and B work together to complete the rest of a job in 7 days. However,\(\frac{{37}}{{100}}\) the job was already done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

 

  • 1] 20
  • 2] 25
  • 3] 30
  • 4] 10
Solution
5
Discuss

If 28 men complete \(\frac{7}{8}\) of a piece of work in a week, then the number of men, who must be engaged to get the remaining work completed in another week, is = ?

 

  • 1] 5
  • 2] 6
  • 3] 4
  • 4] 3
Solution
6
Discuss

A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is = ?

  • 1] 30 days
  • 2] 27 days
  • 3] 20 days
  • 4] 25 days
Solution
7
Discuss

If the work done by (x - 1) men in (x + 1) days and the work done by (x + 2) men in (x - 1) days are in the ratio 9 : 10, then the value of x is equal to ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
8
Discuss

A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?

  • 1]

    \(\frac{{80}}{{13}}{ \text{days}}\)

  • 2]

    \(\frac{{70}}{{13}}{ \text{days}}\)

  • 3]

    \(\frac{{75}}{{13}}{ \text{days}}\)

  • 4]

    \(\frac{{60}}{{13}}{ \text{days}}\)

Solution
9
Discuss

The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?

 

  • 1] 4 : 5 : 6
  • 2] 4 : 7 : 5
  • 3] 5 : 7 : 4
  • 4] 5 : 6 : 8
Solution
10
Discuss

16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will they take to complete the remaining work ?

  • 1] 4 days
  • 2] 6 days
  • 3] 8 days
  • 4] 10 days
Solution