Quiz Discussion

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only 58 th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

Course Name: Quantitative Aptitude

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

#Quiz
1
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
10
Discuss

Five men are working to complete a work in 15 days. After five days 10 women are accompanied by them to complete the work in next 5 days. If the work is to be done by women only, then in how many days could the work be over if 10 women have started it ?

  • 1] 10 days
  • 2] 12 days
  • 3] 15 days
  • 4] 18 days
Solution
2
Discuss

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?

  • 1] 36
  • 2] 24
  • 3] 18
  • 4] Cannot be determined
Solution
3
Discuss

A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:

  • 1] 9 days
  • 2] 10 days
  • 3] 11 days
  • 4] 12 days
Solution
4
Discuss

A man can do a piece of work in 30 hours. If he works with his son then the same piece of work is finished in 20 hours. If the son works alone then he do the work in ?

  • 1] 60 hours
  • 2] 50 hours
  • 3] 25 hours
  • 4] 10 hours
Solution
5
Discuss

Two pipes can fill an empty tank separately in 24 minutes and 40 minutes respectively and a third pipe can empty 30 gallons of water per minute. If all three pipes are open, empty tanks become full in one hour. The capacity of the tank (in gallons) is:

  • 1] 800 gallons
  • 2] 600 gallons
  • 3] 500 gallons
  • 4] 400 gallons
Solution
6
Discuss

A boy and a girl together fill a cistern with water. The boy pours 4 liters of water every 3 minutes and girl pours 3 litres every 4 minutes. How much time will it take to fill 100 litres of water in the cistern?

  • 1] 36 minute
  • 2] 42 minutes
  • 3] 48 minutes
  • 4] 44 minutes
Solution
7
Discuss

45 men can complete a piece of work in 16 days. Four days they started working , 36 more men joined them. How many days will they take to complete the remaining work ?

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    623 days

  • 4]

    734 days

Solution
8
Discuss

Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:

  • 1] 3 days
  • 2] 4 days
  • 3] 4.5 days
  • 4] 5.4 days
Solution
9
Discuss

Subhash can copy 50 pages in 10 hours; Subhash and Prakash together can copy 300 pages in 40 hours. In how much time can Prakash copy 30 pages?

  • 1] 13 hour
  • 2] 12 hour
  • 3] 11 hour
  • 4] 9 hour
  • 5] 10 hour