Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Solution |
2
Discuss
|
Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 day. The original number of carpenters was ?
Solution |
3
Discuss
|
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?
Solution |
4
Discuss
|
The laborer's A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days, A and C together can do it in 12 days, while A and B together can do it in \({ \text{13}}\frac{1}{3}\) days. The money will be divided in the ratio?
Solution |
5
Discuss
|
A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?
Solution |
6
Discuss
|
A started a ,work and left after working for 2 days. Then B was called and he finished the work in 9 days. had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working alone, finish the whole work ?
Solution |
7
Discuss
|
A can do three times the work done by B in one day. They together finish \(\frac{2}{5}\) of the work in 9 days. The number of days by which B can do the work alone is?
Solution |
8
Discuss
|
A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
Solution |
9
Discuss
|
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Solution |
10
Discuss
|
A boy and a girl together fill a cistern with water. The boy pours 4 liters of water every 3 minutes and girl pours 3 litres every 4 minutes. How much time will it take to fill 100 litres of water in the cistern?
Solution |