A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

Course Name: Quantitative Aptitude

  • 1]

    20 days

  • 2]

    22 1/2 day

  • 3]

    25 days

  • 4]

    30 days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If two persons, with equal abilities, can do two jobs in two days then 100 persons with equal abilities can do 100 similar jobs in = ?

  • 1] 100 days
  • 2] 10 days
  • 3] 5 days
  • 4] 2 days
Solution
2
Discuss

A is thrice as good a workman as B and so takes 60 days less than B for doing a job. The time in which they can do the job together is = ?

  • 1]

    \(22\frac{1}{2}{ \text{days}}\)

  • 2]

    30 days

  • 3]

    45 days

  • 4]

    60 days

Solution
3
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    \(22\frac{1}{2}\) days

  • 3]

    25 days

  • 4]

    30 days

Solution
4
Discuss

40 men can complete a piece of work in 15 days. 20 more men joined them after 5 days they start doing work. How many days will be required by them to finish the remaining work ?

  • 1]

    \({ \text{7}}\frac{2}{3}{ \text{ days}}\)

  • 2]

    \({ \text{6}}\frac{1}{5}{ \text{ days}}\)

  • 3]

    \({ \text{8}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{6}}\frac{2}{3}{ \text{ days}}\)

Solution
5
Discuss

A does half as much work as B in one -sixth of the time.If together they take 10 days to complete a work, how much time shall B take to do it alone?

  • 1] 13.33 days
  • 2] 20 days
  • 3] 30 days
  • 4] 40 days
Solution
6
Discuss

A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?

  • 1] 5 days
  • 2] 6 days
  • 3] 8 days
  • 4] 7 days
Solution
7
Discuss

At a Tech Pvt Ltd. there are some engineering students employed as trainee engineers, belong to two eminent institutions of India. One group belongs to IIT and another to NIT. Each student of IIT works for 10 hours a day till 60 days and each student of NIT works for 8 hours a day till 80 days on the two same project. The ratio of students of IIT and that of NIT is 4:5 respectively. Students of which institution is slower in work and by how much?

  • 1] IITian is 20% less efficient
  • 2] NITian is 33.33% less efficien
  • 3] NIT is 25% less efficient
  • 4] IIT is 33.33% less efficient
  • 5] Cannot be determined
Solution
8
Discuss

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?

  • 1]

    \(\frac{7}{{24}}{ \text{days}}\)

  • 2]

    \({ \text{3}}\frac{3}{7}{ \text{days}}\)

  • 3]

    4 days

  • 4]

    \({ \text{3}}\frac{1}{{13}}{ \text{days}}\)

Solution
9
Discuss

Working 5 hours a day, A can Complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in:

  • 1] 3 days
  • 2] 4 days
  • 3] 4.5 days
  • 4] 5.4 days
Solution
10
Discuss

A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?

  • 1]

    11 days

  • 2]

    13 days

  • 3]

    20 3/17 days

  • 4]

    None of these

Solution
# Quiz