A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?

Course Name: Quantitative Aptitude

  • 1]

    \(\frac{{124}}{{13}}\) days

  • 2]

    \(\frac{{113}}{{13}}\) days

  • 3]

    \(\frac{{108}}{{13}}\) days

  • 4]

    \(\frac{{131}}{{13}}\) days

  • 5]

    \(\frac{{120}}{{13}}\) days

Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?

  • 1] 20 days
  • 2] 24 days
  • 3] 36 days
  • 4] 72 days
Solution
2
Discuss

A contractor undertook to do a certain piece of work in 9 days. He employed certain number of men, but 6 of them being absent from the very first day, the rest could finish the work in 15 days. The number of men originally employed were

  • 1]

    12

  • 2]

    15

  • 3]

    18

  • 4]

    24

Solution
3
Discuss

3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

  • 1] 20 days
  • 2] 10 days
  • 3] 4 days
  • 4] 15 days
Solution
4
Discuss

Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?

  • 1] 7 hours, 30 minutes
  • 2] 8 hours
  • 3] 8 hours, 15 minutes
  • 4] 8 hours, 25 minutes
Solution
5
Discuss

12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?

  • 1]

    \({ \text{20}}\frac{4}{7}{ \text{ days}}\)

  • 2]

    \({ \text{2}}\frac{4}{7}{ \text{ days}}\)

  • 3]

    \({ \text{20}}\frac{3}{7}{ \text{ days}}\)

  • 4]

    18 days

Solution
6
Discuss

If 10 men can do a piece of work in 12 days, the time taken by 12 men to do the same piece of work will be:

  • 1] 12 days
  • 2] 10 days
  • 3] 9 days
  • 4] 8 days
Solution
7
Discuss

A can do a certain work in 12 days. B is 60% more efficient then A. How many days will B and A together take to do the same job?

  • 1]

    \(\frac{{80}}{{13}}{ \text{days}}\)

  • 2]

    \(\frac{{70}}{{13}}{ \text{days}}\)

  • 3]

    \(\frac{{75}}{{13}}{ \text{days}}\)

  • 4]

    \(\frac{{60}}{{13}}{ \text{days}}\)

Solution
8
Discuss

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone ?

  • 1] 10 days
  • 2] 9 days
  • 3] 12 days
  • 4] 15 days
Solution
9
Discuss

A and B can compete a piece of work in 18 days. They worked together for 12 days and then A left. B alone finished the work in 15 days. If Rs. 1500 be paid for the work then A's share is:

  • 1] Rs. 750
  • 2] Rs. 800
  • 3] Rs. 600
  • 4] Rs. 900
Solution
10
Discuss

Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?

  • 1] 3y : 2x
  • 2] 2x : 3y
  • 3] x : y
  • 4] 2y : 3x
Solution
# Quiz