Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?

Course Name: Quantitative Aptitude

  • 1] 7 hours, 30 minutes
  • 2] 8 hours
  • 3] 8 hours, 15 minutes
  • 4] 8 hours, 25 minutes
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  • 1]

    13 * 1/3 days

  • 2]

    15 days

  • 3]

    20 days

  • 4]

    26 days

Solution
2
Discuss

A group of 12 men can do a piece of work in 14 days and other group of 12 women can do the same work in 21 days. They begin together but 3 days before the completion of work, man's group leaves off. The total number of days to complete the work is:

  • 1]

    \(\frac{{65}}{4}\)

  • 2]

    \(\frac{{93}}{3}\)

  • 3]

    \(\frac{{51}}{5}\)

  • 4]

    60

Solution
3
Discuss

A and B working together completed a job in 5 days. If A works twice as efficiently as he actually did and B works \(\frac{1}{3}\) of actual efficiency, the work would have been completed in 3 days. Find the for A to complete the job alone.

 

  • 1]

    \(6\frac{1}{2}\)

  • 2]

    \(6\frac{1}{4}\)

  • 3]

    \(6\frac{3}{4}\)

  • 4]

    \(12\frac{1}{2}\)

  • 5]

    None of these

Solution
4
Discuss

A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 1]

    20 days

  • 2]

    22 1/2 day

  • 3]

    25 days

  • 4]

    30 days

Solution
5
Discuss

A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before completion. The number of days for which C worked is

  • 1]

    4

  • 2]

    8

  • 3]

    12

  • 4]

    24

Solution
6
Discuss

A and B can together finish a work in 30 days. They worked together for 20 days and B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the job ?

  • 1] 40 days
  • 2] 50 days
  • 3] 54 days
  • 4] 60 days
Solution
7
Discuss

If 10 men or 20 boys can make 260 mats in 20 days, then how many mats will be made by 8 men and 4 boys in 20 days?

  • 1] 260
  • 2] 240
  • 3] 280
  • 4] 520
Solution
8
Discuss

A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only \({\frac{5}{8}}\) th of the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

 

  • 1] 16
  • 2] 12
  • 3] 10
  • 4] 18
Solution
9
Discuss

An employee pays Rs. 26 for each day a worker and forfeits Rs. 7 for each day he idle. At the end of 56 days, if the worker got Rs. 829, for how many days did the worker remain idle?

  • 1] 21
  • 2] 15
  • 3] 19
  • 4] 13
  • 5] 17
Solution
10
Discuss

Five men are working to complete a work in 15 days. After five days 10 women are accompanied by them to complete the work in next 5 days. If the work is to be done by women only, then in how many days could the work be over if 10 women have started it ?

  • 1] 10 days
  • 2] 12 days
  • 3] 15 days
  • 4] 18 days
Solution