A and B together can complete a job in 8 days. Both B and C, working alone can finish the same job in 12 days, A and B commence work on the job, and work for 4 days, where upon A leaves, B continues for 2 more days, and then he leaves too, C now starts working, and finishes the job. How many days will C require to finish the remaining work ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are ?
Solution |
2
Discuss
|
A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?
Solution |
3
Discuss
|
A can build a wall in the same time in which B and C together can do it. If A and B together can do it. If A and B together could do it in 25 days and C alone in 35 days, in what time could B alone do it ?
Solution |
4
Discuss
|
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
Solution |
5
Discuss
|
Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?
Solution |
6
Discuss
|
12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?
Solution |
7
Discuss
|
A can do half of a piece of work in 1 day,where B can do full. B can do half the work as C in 1 day. The ratio of their efficiencies of work is = ?
Solution |
8
Discuss
|
A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?
Solution |
9
Discuss
|
A and B working separately can do a piece of work in 9 and 15 days respectively. If they work for a day alternately, with A beginning, then the work will be completed in:
Solution |
10
Discuss
|
If 20 women can lay a road of length 100m in 10 days. 10 women can lay the same road of length 50m in = ?
Solution |