A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in = ?

Course Name: Quantitative Aptitude

  • 1] 8 days
  • 2] 6 days
  • 3] 8 days
  • 4] 12 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?

  • 1] 30
  • 2] 10
  • 3] 18
  • 4] 28
Solution
2
Discuss

Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:

  • 1]

    15

  • 2]

    16

  • 3]

    18

  • 4]

    25

Solution
3
Discuss

12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?

  • 1] 4 minutes
  • 2] 10 minutes
  • 3] 12 minutes
  • 4] 8 minutes
Solution
4
Discuss

Three pipes A,B and C attached to a cistern. A can fill it in 10 min, B in 15 min, C is a waste pipe for emptying it. After opening both the pipes A and B, a man leaves the cistern and returns when the cistern should have been just full. Finding, however, that the waste pipe had left open, he closes it and the cistern now gets filled in 2 min. In how much time the pipe C, if opened alone, empty the full cistern?

  • 1] 12 min
  • 2] 16 min
  • 3] 18 min
  • 4] 15 min
  • 5] None of these
Solution
5
Discuss

A can do a bit of work in 8 hours while B along can do it in 12 hours. Both A and B cooperating can complete the work in:

  • 1]

    10 hours

  • 2]

    4 hours

  • 3]

    21/4 hours

  • 4]

    24/5 hours

Solution
6
Discuss

18 men or 36 boys working 6 hours a day can plough a field in 24 days. In how many days will 24 men and 24 boys working 9 hours a day plough the same field ?

  • 1] 9 days
  • 2] 10 days
  • 3] 6 days
  • 4] 8 days
Solution
7
Discuss

P and Q together can do a job in 6 days. Q and R can finish the same job in \(\frac{{60}}{7}\) days. P started the work and worked for 3 days. Q and R continued for 6 days to finish the work. Then the difference of days in which R and P can complete the alone is P can complete the job alone is ?

 

  • 1] 10 days
  • 2] 8 days
  • 3] 12 days
  • 4] 15 days
Solution
8
Discuss

Dinesh and Rakesh are working on an Assignment, Dinesh takes 6 hours to type 32 pages on a computer, while Rakesh takes 5 hours to type 40 pages. How much time will they take working together on two different computers to type an assignment of 110 page ?

  • 1] 7 hours, 30 minutes
  • 2] 8 hours
  • 3] 8 hours, 15 minutes
  • 4] 8 hours, 25 minutes
Solution
9
Discuss

Two men undertake to do a piece of work for Rs. 1400. The first man alone can do this work in 7 days while the second man alone can do this work in 8 days. If they working together complete this work in 3 days with the help of a boy, how should the money be divided ?

  • 1] Rs. 600, Rs. 550, Rs. 250
  • 2] Rs. 600, Rs. 525, Rs. 275
  • 3] Rs. 600, Rs. 500, Rs. 300
  • 4] Rs. 500, Rs. 525, Rs. 375
Solution
10
Discuss

A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?

  • 1] 60 days
  • 2] 54 days
  • 3] 48 days
  • 4] 50 days
Solution