40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?
Solution |
10
Discuss
|
A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?
Solution |
2
Discuss
|
A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Solution |
3
Discuss
|
A boy and a girl together fill a cistern with water. The boy pours 4 liters of water every 3 minutes and girl pours 3 litres every 4 minutes. How much time will it take to fill 100 litres of water in the cistern?
Solution |
4
Discuss
|
Vimal can do a piece of work in 20 days, Vimal and Kamal together can do in 12 days. If Kamal does the work only for half a day daily then in how many days the work will be completed ?
Solution |
5
Discuss
|
Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?
Solution |
6
Discuss
|
A, B and C can complete a piece of work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work was ?
Solution |
7
Discuss
|
If one pipe A can fill a tank in 20 minutes, then 5 pipes, each of 20% efficiency of A, can fill the tank in:
Solution |
8
Discuss
|
A does 20% less work than B. If A can complete a piece of work in 712 hours, then B can do it in?
Solution |
9
Discuss
|
Ram Lal is a renowned packager of fruits in Varanasi. He packs 70 mangoes or 56 guavas every day working 7 hours a day. His wife also helps him. She packs 30 mangoes or 24 guavas working 6 hours per day. Ram Lal has to pack 3300 mangoes and 2400 guavas with help of his wife. They works alternately, each day 10 hours. His wife started packaging firs day and works every alternate days. Similarly, Ram Lal started his work second day and and worked alternatively till the completion of the work. In how many days the work will finished?
Solution |