Quiz Discussion

There is provision of food in fort for 1200 soldiers for 60 days. After 15 days, 200 soldiers leave the fort. Remaining food will last for how many days?

Course Name: Quantitative Aptitude

  • 1] 56 days
  • 2] 50 days
  • 3] 54 days
  • 4] 48 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

If 20 women can lay a road of length 100m in 10 days. 10 women can lay the same road of length 50m in = ?

  • 1] 5 days
  • 2] 15 days
  • 3] 10 days
  • 4] 20 days
Solution
2
Discuss

Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?

  • 1] 3y : 2x
  • 2] 2x : 3y
  • 3] x : y
  • 4] 2y : 3x
Solution
3
Discuss

A can do a certain job in 12 days and B is 60% more efficient than A. The B can do the same piece of work in ?

  • 1]

    \({ \text{8 days}}\)

  • 2]

    \({ \text{7}}\frac{1}{2}{ \text{ days}}\)

  • 3]

    \({ \text{6}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{6 days}}\)

Solution
4
Discuss

A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time. Then B left the work. If A completed the rest of the work in 10 days, then B worked for

  • 1]

    6 days

  • 2]

    8 days

  • 3]

    12 days

  • 4]

    16 days

Solution
5
Discuss

639 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons working 6 hours a day complete the work ?

  • 1] 210 days
  • 2] 213 days
  • 3] 214 days
  • 4] 215 days
Solution
6
Discuss

An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 1] 43
  • 2] 45
  • 3] 55
  • 4] 68
  • 5] 60
Solution
7
Discuss

A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?

  • 1] 3 days
  • 2] 6 days
  • 3] 12 days
  • 4] 24 days
Solution
8
Discuss

If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many days can A alone complete the work?

  • 1] 60
  • 2] 45
  • 3] 40
  • 4] 30
Solution
9
Discuss

A is 60% more efficient than B. In how many days will A and B working together complete a piece of work which A alone takes 15 days to finish?

  • 1]

    \(\frac{{124}}{{13}}\) days

  • 2]

    \(\frac{{113}}{{13}}\) days

  • 3]

    \(\frac{{108}}{{13}}\) days

  • 4]

    \(\frac{{131}}{{13}}\) days

  • 5]

    \(\frac{{120}}{{13}}\) days

Solution
10
Discuss

12 monkeys can eat 12 bananas in 12 minutes. In how many minutes can 4 monkeys eat 4 bananas ?

  • 1] 4 minutes
  • 2] 10 minutes
  • 3] 12 minutes
  • 4] 8 minutes
Solution