A and B together can complete a task in 20 days. B and C together can complete the same task in 30 days. A and C together can complete the same task in 40 days. What is the respective ratio of the number of days taken by A when completing the same task alone to the number of days taken by C when completing the same task alone?
2:5
2:7
3:7
1:5
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?
Solution |
2
Discuss
|
12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men do this work ?
Solution |
3
Discuss
|
There is a group of 5 boys and 2 girls. The two groups working together can do four times as much work as a boy and a girl. Ratio of working capacities of a boy and a girl is:
Solution |
4
Discuss
|
A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?
Solution |
5
Discuss
|
A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?
Solution |
6
Discuss
|
A contractor undertake to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the work in men, how many days behind the scheduled the work should have been finished ?
Solution |
7
Discuss
|
A man and a boy can do a piece of work in 24 days. If the man works alone for the last 6 days, it is completed in 26 days. How long would the boy take to do it alone ?
Solution |
8
Discuss
|
12 men can do a piece of work in 15 days and 20 women can do the same work in 12 days. In how many days can 5 men and 5 women complete the same work ?
Solution |
9
Discuss
|
A single person takes 10 minutes to stitch a bag. If from 10.00 a.m. to 12.30 p.m., 1245 bags are to be stitched how many persons should be employed on this job?
Solution |
10
Discuss
|
A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?
Solution |