A is thrice good a workman as B and therefore is able to finish a job in 40 days less than B. Working together they can do it in:

Course Name: Quantitative Aptitude

  • 1] 15 days
  • 2] 16 days
  • 3] 18 days
  • 4] 20 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A does half as much work as B in one-sixth of the time. If together they take 10 days to complete a work. How much time shall B alone take to do it ?

  • 1] 30 days
  • 2] 40 days
  • 3] 50 days
  • 4] 70 days
Solution
2
Discuss

A can do a work in 10 days. The efficiency of A is 20% less than B. How many days B need to finish the same work?

  • 1] 8.5 days
  • 2] 12.3 days
  • 3] 8 days
  • 4] 7.5 days
Solution
3
Discuss

A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed ?

  • 1] 4
  • 2] 5
  • 3] 7
  • 4] 8
Solution
4
Discuss

If 20 women can lay a road of length 100m in 10 days. 10 women can lay the same road of length 50m in = ?

  • 1] 5 days
  • 2] 15 days
  • 3] 10 days
  • 4] 20 days
Solution
5
Discuss

A sum of money is sufficient to pay A's wages for 21 days and B's wages for 28 days. The same money is sufficient to pay the wages of both for ?

  • 1] 12 days
  • 2] 13 days
  • 3] 14 days
  • 4] 15 days
Solution
6
Discuss

A cistern can be filled by two pipes in 20 and 30 minutes respectively. Both pipes being opened, when the first pipe must be turned off so that the cistern may be filled in 10 minutes more.

  • 1] After 10 minutes
  • 2] After 12 minutes
  • 3] After 20 minutes
  • 4] After 8 minutes
Solution
7
Discuss

The time taken by 4 men to complete a job is double the time taken by 5 children to complete the same job. Each man is twice as fast as a woman. How long will 12 men, 10 children and 8 women take to complete a job, given that a child would finish the job in 20 days ?

  • 1] 4 days
  • 2] 2 days
  • 3] 1 day
  • 4] 10 days
Solution
8
Discuss

Amit, Bhawana and Chandan can do a piece of work, working together in one day only. Amit is 5 times efficient than Bhawna and Chandan takes half of the number of days taken by Bhawna to do the same work. What is the difference between the number of days taken by Amit and Chandan when they work alone ?

  • 1]

    4

  • 2]

    5

  • 3]

    3

  • 4]

    \({ \text{2}}\frac{2}{5}\)

Solution
9
Discuss

X can copy 80 pages in 20 hours, x and y together can copy 135 pages in 27 hours. Then y can copy 20 pages in ?

  • 1] 20 hours
  • 2] 24 hours
  • 3] 3 hours
  • 4] 12 hours
Solution
10
Discuss

A particular job can be completed by a team of 10 men in 12 days. The same job can be completed by a team of 10 women in 6 days. How many days are needed to complete the job if the two teams work together ?

  • 1] 4 days
  • 2] 6 days
  • 3] 9 days
  • 4] 18 days
Solution
# Quiz