A and B can together do a piece of work it in 6 days and A alone can do it in 9 days. The number of days B will take to do it alone is ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of the wall ?
Solution |
2
Discuss
|
Subhash can copy 50 pages in 10 hours; Subhash and Prakash together can copy 300 pages in 40 hours. In how much time can Prakash copy 30 pages?
Solution |
3
Discuss
|
A and B together can complete a particular task in 4 days. If A alone can complete the same task in 12 days. How many days will B take to complete the task if he works alone?
Solution |
4
Discuss
|
639 persons can repair a road in 12 days working 5 hours a day. In how many days will 30 persons working 6 hours a day complete the work ?
Solution |
5
Discuss
|
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is = ?
Solution |
6
Discuss
|
To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :
Solution |
7
Discuss
|
A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?
Solution |
8
Discuss
|
Ganga and Saraswati, working separately can mow field in 8 and 12 hours respectively. If they work in stretches of one hour alternately. Ganga is beginning at 9 a.m., when will the moving be completed?
Solution |
9
Discuss
|
If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in:
Solution |
10
Discuss
|
4 men and 10 women were put on work. They completed \(\frac{1}{3}\) of the work in 4 days. After this 2 men and 2 women were increased. They completed \(\frac{2}{9}\) more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased?
Solution |