25 men with 10 boys can do in 6 days as much work as 21 men with 30 boys can do in days. How many boys must help 40 men to do the same work in 4 days ?
Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api
# | Quiz |
---|---|
1
Discuss
|
Two men and women are entrusted with a task. The second man needs three hours more to cope up with the job than the second man and the woman would need working together. The first man, working alone, would need as much time as second man and the woman working together. The first man working alone, would spend eight hours less than the double period of the time second man would spend working alone. How much time would the two men and the women need to complete the task if they all asked together?
Solution |
2
Discuss
|
A and B can compete a piece of work in 18 days. They worked together for 12 days and then A left. B alone finished the work in 15 days. If Rs. 1500 be paid for the work then A's share is:
Solution |
3
Discuss
|
3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?
Solution |
4
Discuss
|
20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined. In how many days is the remaining work completed ?
Solution |
5
Discuss
|
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
Solution |
6
Discuss
|
A and B can together finish a piece of work in 30 days. They worked on it 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish the work in = ?
Solution |
7
Discuss
|
Two pipes can fill the cistern in 10hr and 12 hr respectively, while the third empty it in 20hr. If all pipes are opened simultaneously, then the cistern will be filled in:
Solution |
8
Discuss
|
A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ?
Solution |
9
Discuss
|
A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?
Solution |
10
Discuss
|
6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required ?
Solution |