10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days ?

Course Name: Quantitative Aptitude

  • 1] 6 hours/day
  • 2] 10 hours/day
  • 3] 12 hours/day
  • 4] 15 hours/day
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in :

  • 1]

    4 days

  • 2]

    6 days

  • 3]

    8 days

  • 4]

    12 days

Solution
2
Discuss

A can do a piece of work in 10 days, B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get Rs. 1500 for the whole work, the daily wages of B and C are ?

  • 1] Rs. 150
  • 2] Rs. 225
  • 3] Rs. 250
  • 4] Rs. 300
Solution
3
Discuss

A can do a piece of work in 15 days, which B can do it in 10 days. B worked at it for 8 days. A can finish the remaining work in?

  • 1] 2 days
  • 2] 3 days
  • 3] 5 days
  • 4] 10 days
Solution
4
Discuss

Subhash can copy 50 pages in 10 hours; Subhash and Prakash together can copy 300 pages in 40 hours. In how much time can Prakash copy 30 pages?

  • 1] 13 hour
  • 2] 12 hour
  • 3] 11 hour
  • 4] 9 hour
  • 5] 10 hour
Solution
5
Discuss

If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then number of chairs made by 18 carpenters in 360 days each working 8 hours a day ?

  • 1] 1320
  • 2] 1380
  • 3] 1260
  • 4] 920
Solution
6
Discuss

To complete a piece of work A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C will take :

  • 1] 7 Days
  • 2] 7.5 Days
  • 3] 8 Days
  • 4] 8.5 Days
Solution
7
Discuss

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is = ?

  • 1] 20 days
  • 2] 21 days
  • 3] 22 days
  • 4] 24 days
Solution
8
Discuss

A group of workers can complete a piece of work in 50 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one person joins them and this process continues till the work is completed. How many approximate days are needed to complete the work ?

  • 1] 8 days
  • 2] 9 days
  • 3] 10 days
  • 4] 11 days
Solution
9
Discuss

A road of 5 m length will be constructed in 100 days. So, 280 workers were employed. But after 80 days it was found that only \({ \text{3}}\frac{1}{2}\) km road was completed. Now, how many more people were needed to finish the work in the specified time?

 

  • 1] 480
  • 2] 80
  • 3] 200
  • 4] 100
Solution
10
Discuss

A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work. A leaves off. The total number of days to complete the work is ?

  • 1]

    \({ \text{6}}\frac{3}{5}\)

  • 2]

    \({ \text{8}}\frac{1}{2}\)

  • 3]

    \({ \text{10}}\frac{1}{5}\)

  • 4]

    \({ \text{13}}\frac{1}{2}\)

Solution
# Quiz