Quiz Discussion

Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is = ?

Course Name: Quantitative Aptitude

  • 1] 12 days
  • 2] 14 days
  • 3] 36 days
  • 4] 40 days
Solution
No Solution Present Yet

Top 5 Similar Quiz - Based On AI&ML

Quiz Recommendation System API Link - https://fresherbell-quiz-api.herokuapp.com/fresherbell_quiz_api

# Quiz
1
Discuss

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work ?

  • 1]

    \({ \text{ 4}}\frac{4}{5}{ \text{ days}}\)

  • 2]

    \({ \text{ 3}}\frac{1}{3}{ \text{ days}}\)

  • 3]

    \({ \text{ 5}}\frac{1}{4}{ \text{ days}}\)

  • 4]

    \({ \text{2}}\frac{2}{3}{ \text{ days}}\)

Solution
2
Discuss

If 5 men and 3 women can reap 18 acre of crop in 4 days, 3 men and 2 women can reap 22 acre of crop in 8 days, then how many men are required to join 21 women to reap 54 acre of crop in 6 days ?

  • 1] 5
  • 2] 6
  • 3] 10
  • 4] 12
Solution
3
Discuss

The daily wages of A and B respectively are Rs. 3.50 and Rs. 2.50. When A finishes a certain work, he gets a total wage of Rs. 63. When B does the same work, he gets a total wage Rs. 75. If both of them do it together what is cost of the work ?

  • 1] Rs. 67.50
  • 2] Rs. 27.50
  • 3] Rs. 60.50
  • 4] Rs. 70.50
Solution
4
Discuss

Two men can do a piece of work in x days. But y women can do that in 3 days. Then the ratio of the work done by 1 man and 1 woman is ?

  • 1] 3y : 2x
  • 2] 2x : 3y
  • 3] x : y
  • 4] 2y : 3x
Solution
5
Discuss

A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will get ?

  • 1] A Rs. 24, B Rs. 54, C Rs. 162
  • 2] A Rs. 22, B Rs.50, C Rs. 132
  • 3] A Rs. 26, B Rs. 52, C Rs. 142
  • 4] A Rs. 20, B Rs. 44, C Rs. 182
Solution
6
Discuss

Two pipes can fill the cistern in 10hr and 12 hr respectively, while the third empty it in 20hr. If all pipes are opened simultaneously, then the cistern will be filled in:

  • 1] 7.5 hr
  • 2] 8 hr
  • 3] 8.5 hr
  • 4] 10 hr
Solution
7
Discuss

Kamal can do a work in 15 days. Bimal is 50% more efficient then Kamal. The number of days, Bimal will take to do the same piece of work, is = ?

  • 1]

    \(7\frac{1}{2}\)

  • 2]

    10

  • 3]

    12

  • 4]

    14

Solution
8
Discuss

If the work done by (x - 1) men in (x + 1) days and the work done by (x + 2) men in (x - 1) days are in the ratio 9 : 10, then the value of x is equal to ?

  • 1] 5
  • 2] 6
  • 3] 7
  • 4] 8
Solution
9
Discuss

If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m ?

  • 1] 30
  • 2] 10
  • 3] 18
  • 4] 28
Solution
10
Discuss

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in ?

  • 1]

    \(\frac{7}{{24}}{ \text{days}}\)

  • 2]

    \({ \text{3}}\frac{3}{7}{ \text{days}}\)

  • 3]

    4 days

  • 4]

    \({ \text{3}}\frac{1}{{13}}{ \text{days}}\)

Solution
# Quiz